LESSON
ANSWER KEY AND FEEDBACK
Item
Correct Answer and Feedback
1.
B. 50. (page 5, para 4)
2.
D. 550 meters. (page 7, para 4)
3.
B. Section, FSU, and stack. (page 9, paras 1 and 2)
4.
A. 700 meters. (page 8, Table 1)
5.
D. The storage section. (page 2, para 7)
6.
A. The primary entrance. (page 5, para 3)
7.
C. The vehicle holding area. (page 5, para 4)
8.
D. 700 meters. (page 5, para 5)
9.
A. DA Pamphlet 710-2-2. (page 7, para 2)
10.
D. PSP/M8A1. (page 7, para 4)
11.
Item
Stacks Needed
D544
twelve at 20 tons each
D541
seven (six at 20 tons each and one at five tons)
D540
seven (six at 20 tons each and one at five tons)
N528
one
D552
one
D680
thirteen (twelve at 20 tons each and one at 10 tons)
D675
five (four at 20 tons each and one at 10 tons)
D676
five (four at 20 tons each and one at 10 tons)
D662
five (four at 20 tons each and one at 10 tons)
D681
one
A total of 57 stacks and three FSUs (two at 400 tons each and one at 224 tons) are required. (page 12, Figure 4)
12.
C.
100 feet. (page 12, Figure 4, Note 2)
13.
D.
300 feet. (page 12, Figure 4)
14.
B.
750 feet. (page 12, Figure 4)
15.
D.
1,500 feet. (page 12, Figure 4)