The SOP will be in English. If the employee is foreign speaking, the SOP
must be in his native tongue, also.
The SOP must be approved by the
commander or by a qualified member of his staff, and the personnel
responsible for the performance of an operation. Applicable portions of the
approved SOP must be conspicuously and conveniently posted for all stations
involved in the operation for the personnel's guidance.
PRACTICE EXERCISE
The following items will test the material covered in this lesson. There is
only one correct answer for each item.
When you have completed the
exercise, check your answers with the answer key. If you answer any item
incorrectly, study the part you missed.
SITUATION:
You
have
been
tasked
to
inspect
an
maintenance
facility.
1.
On a rectangular shaped maintenance facility having gable or hip roofs
154 feet in length, how many down connectors are required?
A. 1
B. 2
C. 3
D. 4
2.
system.
How far should the test ground rod be from the system being
tested?
A. 50 feet.
B. 40 feet.
C. 25 feet.
D. 10 feet.